Loading...

Construction projects in the UAE generate two categories of unpaid debt: invoices for work completed but not paid, and retention money withheld at the end of a project. Both categories are recoverable under UAE law, but the recovery process differs depending on whether the amount is undisputed or subject to a defects argument.

Unpaid Construction Invoices: The Recovery Path

For completed construction work where the client has accepted delivery but not paid, the Amr Al Ada’ payment order under Federal Decree-Law No. 42 of 2022 is the primary instrument. The undisputed nature of the debt — demonstrated by signed completion certificates, approved payment applications, or previous partial payments — is the key. If the work is accepted and the invoice is documented, the Amr Al Ada’ converts that documented acceptance into an enforceable court title in 2-4 weeks.

Retention Money: Specific Challenges

Construction retention in the UAE is typically 5-10% of the contract value held by the client for 12-24 months after project completion as security against defects. When the retention period expires and the client refuses to release, the recovery options are: Amr Al Ada’ if the defects liability period has ended and no genuine defects exist, or civil litigation if the client raises defects claims that need to be disputed.

The key tactic for disputed retention: separate the undisputed portion (completed work payment minus any legitimate retention) from the disputed retention and pursue both simultaneously rather than allowing a retention dispute to block payment for the undisputed invoiced work.

Construction retention release dispute Dubai: Amr Al Ada’ payment order under Federal Decree-Law No. 42 of 2022 — enforceable title in 2–4 weeks for undisputed amounts. Article 401 of Federal Decree-Law No. 50 of 2022 — bank account freeze within 24–48 hours for dishonoured post-dated security cheques. UAE civil limitation: 15 years.

2–4 wks
Amr Al Ada’ (undisputed)
24–48 h
Art. 401 (PDC)
Parallel
Undisputed + retention

A Turkish MEP contractor is owed AED 1.35 million by a Dubai main contractor: AED 850,000 in unpaid final account invoices (undisputed, signed completion certificate) + AED 500,000 in retention (disputed — main contractor claims defects on 30% of the retention). Strategy: Amr Al Ada’ immediately for the AED 850,000 undisputed amount. Separate formal defects-liability dispute process for the AED 500,000 retention with a 60-day deadline. Do not allow the disputed retention to block enforcement on the AED 850,000. Amr Al Ada’ application filed Day 10. Main contractor pays AED 850,000 on Day 22. Retention dispute settled at AED 420,000 over the following 45 days. Total recovery: AED 1.27 million. An unpaid invoice in the UAE does not have to become a write-off. Contact Cosmopolite for a free case assessment. No win, no fee.

Subscribe to our Newsletter

Get New Posts to Your Inbox

A successful marketing plan relies heavily on the pulling-power of advertising copy. Writing result-oriented ad copy is difficult. 

Thank you! Your submission has been received!
Oops! Something went wrong while submitting the form.